As a direct or indirect result of the COVID-19 pandemic and uncertainty in a global economy, various issues have been adversely impacting the construction industry, such as an increase in raw material price and supply chain disruption. Particularly, contractors and subcontractors are struggling with their cash flow due to their outstanding payments for the works carried out.
Accordingly, security of payment legislation in each state has played a role in ensuring that anyone carrying out construction work, and supplying related goods and services under a construction contract gets paid promptly. This article discusses and explains your rights under the NSW Security of Payment Act, and each state has its own security of payment legislation, which may differ from each other in detail.
Know Your Rights
In New South Wales, the relevant security of payment legislation is the Building and Construction Industry Security of Payment Act 1999 (NSW) (“SOPA”).
The significance of the SOPA is that it grants contractors rights to receive progress payment even if there is no formal written contract or even if a contract says that you are only allowed to receive a payment at the end of works, i.e., after the completion of works.
Fundamentally, the SOPA entitles a person or a company, who carried out construction work or supplied construction related goods and services, to receive progress payment. A progress payment means a partial payment for works as the project progresses even if the assigned works are not completed. Therefore, the progress payment facilitates cash flow for contractors and suppliers in the construction industry.
Under SOPA, the following rights are granted to you:
Who is entitled to receive a progress payment?
A person or company who, under a construction contract or any other construction arrangement, has undertaken to carry out construction work or supply construction related goods or services in New South Wales is eligible to receive a progress payment under the SOPA.[1]
The “construction work” is broadly defined, including construction, alteration, repair, maintenance or demolition of buildings or structures forming part of land.[2] The “related goods and services” also include various related goods and services such as materials for construction or plant for use in construction work, labour service, design or engineering service.[3]
While the SOPA is drafted to cover contractors, subcontractors, suppliers and service providers as broadly as possible, it should be noted that there are also exceptions such as those engaged in the extraction of oil, natural gas or minerals.
Payment Claims
The procedure for receiving a progress payment is triggered by a person entitled under the SOPA (Claimant) making a Payment Claim in writing to the other person who is responsible to make a payment under a construction contract (Respondent)
In making a Payment Claim, Claimants must ensure that the following requirements are met:[4]
1) The construction work related to the progress payment must be identified;
2) The amount of the progress payment must be indicated;
3) A statement that a Payment Claim is made under this SOPA must be inserted;
4) A Payment Claim must be served on the Respondent within 12 months after the construction work was last carried out; and
5) A Payment Claim is only made one (1) time in a month on and from the last day of each month in which the construction work was carried out.
How to respond to a Payment Claim?
The Respondent is required to respond to the Payment Claim by providing a Payment Schedule to the Claimant within 10 business days after receipt of the Payment Claim. By failing to do so, the amount claimed in the Payment Claim is fixed and Respondents are liable for such amount on the due date.
In issuing a Payment Schedule, Respondents also are required to comply with the following requirements:[5]
1) A Payment Claim related to a Payment Schedule must be identified;
2) The amount of the payment the Respondents propose to make must be indicated; and
3) If applicable, reasons why the amount in the Payment Schedule is less than that in the Payment Claim and reasons for withholding payment must be identified.
Maximum payment terms
One of the most important benefits available under the SOPA is that there are statutory deadlines for a progress payment to be made.[6]
If the Respondents fail to pay the progress payment by the deadline in the diagram below, such amount is deemed due and payable, and interest on the unpaid amount is also payable at the prescribed rate.
Your rights to suspend works
A Claimant also has a right to suspend construction work or supply of related goods and services if a Respondent fails to pay the amount by the due date for payment as described above.[7]
At least two (2) business days prior to the suspension, the Claimant must serve on the Respondent a Notice of Intention to Suspend Work in writing. As the date on which the Notice is given is not counted, the Claimant is eligible to suspend work on and from the fourth day of the Notice. Please see the above diagram.
Once the work is suspended under SOPA, the Claimant is not liable for any loss or damage suffered by the Respondent as a result of such suspension. However, once the whole outstanding amount is paid, the Claimant must resume the work within three (3) business days from the payment date.
Don’t wait until a head contractor gets paid
The SOPA expressly prohibits and invalidates any clause in a construction contract that the payment of money is contingent on a milestone or an event in other contracts including a head contract.[8] A common example of these clauses is that a payment under a subcontract is made upon the payment by a principal under a head contract or upon the practical completion of a head contract. Such clauses are deemed unenforceable under the SOPA, and you have a right to claim the progress payment regardless of the operation of other contracts.
Adjudication
A person eligible under the SOPA also can start an adjudication process for unpaid or disputed progress payments. Adjudication is an informal and independent process which an issue or issues are determined by an independent adjudicator regarding the payment claims. The adjudicator’s determination can be enforced as if it is a judgment rendered in a Court.
However, the Claimant must file an adjudication application in writing by the following deadlines:[9]
Type | Deadline |
When: 1) Respondent issues a Payment Schedule, and 2) the amount in a Payment Schedule is less than the amount in a Payment Claim |
Within 10 business days after a Payment Schedule is issued |
When: 1) Respondent issues a Payment Schedule; and 2) Respondent fails to pay the amount in the Payment Schedule by the due date |
Within 20 business days after a Payment Schedule is issued |
When 1) Respondent fails to issue a Payment Schedule; 2) Respondent fails to pay the amount in a Payment Claim by the due date; 3) Claimant serves written notice of intention to apply for adjudication of the payment claim on Respondent within 20 business days from the due date; and 4) Respondent has been given an opportunity to provide a Payment Schedule within 5 business days after receiving notice of intention to apply for adjudication of the payment claim |
Within 10 business days after the end of the 5 business days for Respondent to provide a Payment Schedule after receiving notice of intention to apply for adjudication of the payment claim |
Payment Withholding
A subcontractor who has made an adjudication application for a progress payment is also entitled to request a principal contractor to retain money owed to a head contractor to cover the claimed amount.[10] This is called a ‘payment withholding request’.
Upon receipt of the payment withholding request, the principal must retain the amount of money to which the payment claim relates.[11]
When a successful outcome is given in the adjudication process, a subcontractor is able to recover the withheld money from the principal through the procedures set out in the Contractors Debts Act 1997 (NSW).
How can we assist
If you are involved in construction work in New South Wales, the SOPA entitles you to claim the progress payment and have protections accordingly. However, your rights under SOPA may vary depending on your satisfactory fulfilment of requirements and on whether you took proper actions in a timely manner.
Although the SOPA sets out a statutory regime for prompt payment for construction work, there are still a number of disputes arising from unpaid progress payments in a construction contract, which ends up with unsatisfactory outcomes for unpaid contractors and suppliers.
If you are unsure what rights you have in your construction payment issues, H & H Lawyers will be happy to review your case to check whether it might fall within a case protected under the Security of Payment Act or other relevant laws. We can further assist in finding a way to enforce your rights.
Disclaimer: The contents of this publication are general in nature and do not constitute legal advice. The information may have been obtained from external sources and we do not guarantee the accuracy or currency of the information at the date of publication or in the future. Please obtain legal advice specific to your circumstances before taking any action on matters discussed in this publication.
[1] SOPA ss4 and 8.
[2] SOPA s5
[3] SOPA s5
[4] SOPA s13
[5] SOPA s14
[6] SOPA s11
[7] SOPA s27
[8] SOPA s12
[9] SOPA s17
[10] SOPA s26A
[11] SOPA s26B